Dzawada'enuxw First Nation - Padakus Hydropower (Construction Phase 2)

Dzawada'enuxw First Nation, British Columbia

completeGreen EnergyRNIS
Federal contribution
$4.5M
$4,459,789
Federal share57%

of $7.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022202320242025
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Dzawada'enuxw First Nation
Construction start
Jun 15, 2023(actual)
Construction end
Nov 26, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2023
  • Construction end2 weeks earlyforecast Dec 10, 2024