Back to projects

Rehabilitation of the J. Henri Séguin Bridge

L'Orignal, Ontario

completeHighways and RoadsMRIF
Federal contribution
$308,883
Federal share33%

of $926.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 20, 2005(actual)
Construction end
Feb 5, 2008(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 15, 2004
  • Construction end2.1 years lateforecast Dec 30, 2005

Also in L'Orignal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11422 in the federal list. How to read these figures.