Construction of a Multi-purpose Pavilion
Federal contribution
$396,478
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 19, 2005
2006
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Greater Fredericton Airport Authority
- Construction start
- Oct 18, 2005(actual)
- Construction end
- Oct 25, 2006(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 5, 2005
- Construction end7 weeks earlyforecast Dec 16, 2006
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11521 in the federal list. How to read these figures.