Rehabilitation of Radcliffe Bridge
Federal contribution
$81,691
Federal share33%
of $245.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Alnwick / Haldimand
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Aug 31, 2006(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end9 months lateforecast Nov 15, 2005
Also in Grafton