Improvements to bridges and culverts
Federal contribution
$106,667
Federal share33%
of $320.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of East Gwillimbury
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Nov 22, 2006(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end12 months lateforecast Nov 30, 2005
Also in Sharon