Improvements to bridges and culverts

Sharon, Ontario

completeHighways and RoadsMRIF
Federal contribution
$106,667
Federal share33%

of $320.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of East Gwillimbury
Construction start
Apr 20, 2005(actual)
Construction end
Nov 22, 2006(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 15, 2004
  • Construction end12 months lateforecast Nov 30, 2005