Replacement of Gibbs Bridge No. 2 and Argue Bridge
Federal contribution
$316,667
Federal share33%
of $950.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Brock
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Sep 25, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end22 months lateforecast Nov 30, 2006
Also in Cannington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11767 in the federal list. How to read these figures.