Construction of trunk watermains and waterlines (The Rural Watermain Servicing Project: Phases 3, 4)
Federal contribution
$4.5M
$4,530,857
Federal share33%
of $13.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Lambton Shores
- Construction start
- Jan 1, 2006(actual)
- Construction end
- May 17, 2010(actual)
Against the original forecast
- Construction start20 months lateforecast May 6, 2004
- Construction end8 months lateforecast Sep 30, 2009
Also in Forest
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11807 in the federal list. How to read these figures.