Replacement of the Wilton Creek, Black Creek, Puzzle Lake Bridges.
Federal contribution
$626,000
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Lennox & Addington
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Feb 6, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end14 months lateforecast Nov 30, 2006
Also in Napanee
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11826 in the federal list. How to read these figures.