Replacement of Nesbitt Bridge

Winchester, Ontario

completeHighways and RoadsMRIF
Federal contribution
$135,000
Federal share33%

of $405.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of North Dundas
Construction start
Apr 20, 2005(actual)
Construction end
Sep 25, 2007(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 24, 2004
  • Construction end9 months lateforecast Dec 31, 2006