Replacement of Nesbitt Bridge
Federal contribution
$135,000
Federal share33%
of $405.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of North Dundas
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Sep 25, 2007(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 24, 2004
- Construction end9 months lateforecast Dec 31, 2006
Also in Winchester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11853 in the federal list. How to read these figures.