Replacement of the Gold Creek Bridge

Ilderton, Ontario

completeHighways and RoadsMRIF
Federal contribution
$264,783
Federal share33%

of $794.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 26, 2005(actual)
Construction end
Sep 12, 2007(actual)

Against the original forecast

  • Construction end12 months lateforecast Aug 30, 2006