Replacement of Eden Mills Bridge
Federal contribution
$152,500
Federal share33%
of $457.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Guelph/Eramosa
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Mar 29, 2006(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2004
- Construction end6 months earlyforecast Sep 30, 2006
Also in Rockwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11878 in the federal list. How to read these figures.