Reconstruction of 15 Sideroad and Two Bridges
Federal contribution
$340,368
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Erin
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Sep 30, 2006(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end13 months earlyforecast Nov 1, 2007
Also in Hillsburgh