Back to projects

Replacement of two bridges in Town of Innisfil

Innisfil, Ontario

completeHighways and RoadsMRIF
Federal contribution
$277,633
Federal share33%

of $832.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Innisfil
Construction start
Apr 30, 2005(actual)
Construction end
Jul 30, 2009(actual)

Against the original forecast

  • Construction end4 months lateforecast Mar 31, 2009

Also in Innisfil

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11939 in the federal list. How to read these figures.