Reconstruction of Tyotown Road
Federal contribution
$550,000
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of South Glengarry
- Construction start
- May 1, 2005(actual)
- Construction end
- Dec 17, 2008(actual)
Against the original forecast
- Construction end24 months lateforecast Dec 31, 2006
Also in Lancaster
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11949 in the federal list. How to read these figures.