Back to projects

Purchase of a vehicle to provide on-demand transportation services in the communities of Rose Valley, Fosston, Archerwill and the Rural Municipality of Ponass Lake, Saskatchewan

Rose Valley, Saskatchewan

completePublic TransitRTSF
Federal contribution
$66,740
Federal share78%

of $85.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 27, 2024
Built

Approved 8 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Sep 1, 2024(actual)
Construction end
Sep 18, 2024(actual)

Against the original forecast

  • Construction start8 months lateforecast Jan 1, 2024
  • Construction end3 months earlyforecast Dec 31, 2024

Also in Rose Valley