Purchase of hybrid vehicles to improve transportation services in the village and surrounding communities of Chéticamp, Nova Scotia.
Federal contribution
$191,357
Federal share80%
of $239.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 7, 2024
Built
Approved 6 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- La Coopérative de transport de Chéticamp Ltée (LAcabie)
- Construction start
- Apr 1, 2024(actual)
- Construction end
- Sep 13, 2024(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 1, 2023
- Construction end7 months earlyforecast Mar 31, 2025