Photovoltaic Project - Acadieville Community Centre
Federal contribution
$167,291
Federal share80%
of $209.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2024
Built
Approved 5 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- La Coopérative des services communautaire d'Acadieville Ltée
- Construction start
- Aug 10, 2024(actual)
- Construction end
- Nov 21, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2024
- Construction end7 weeks lateforecast Sep 30, 2024
Also in Arcadia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121866 in the federal list. How to read these figures.