LWF Community Centre (LWF Hall) Renovation
Federal contribution
$384,648
Federal share80%
of $480.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2024
20242025
Built
Approved 5 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Lakeview, Windsor Junction, Fall River, Firemens Association
- Construction start
- Oct 31, 2023(actual)
- Construction end
- Nov 30, 2025(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 30, 2023
- Construction end16 months lateforecast Jul 31, 2024
Also in Halifax