Legends Arena
Federal contribution
$2.2M
$2,173,097
Federal share79%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 4, 2024
20252026
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Tomorrow's Legends
- Construction start
- Mar 28, 2025(actual)
- Construction end
- Mar 28, 2026(forecast)
Against the original forecast
- Construction start21 months lateforecast Jul 3, 2023
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121876 in the federal list. How to read these figures.