Schedule

Announced and approvedMar 13, 2025
2025
Built

Approved 13 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Aug 12, 2024(actual)
Construction end
Jun 26, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 15, 2024
  • Construction end12 months lateforecast Jun 21, 2024

Also in Halifax