Back to projects

SABRI Transit Improvement Project for St. Anthony, Newfoundland and Labrador

Cook's Harbour, Newfoundland and Labrador

underwayPublic TransitRTSF
Federal contribution
$589,780
Federal share60%

of $989.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
20252026
BuiltForecast

Approved 16 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Feb 3, 2025(actual)
Construction end
Mar 2, 2026(forecast)

Against the original forecast

  • Construction start11 months lateforecast Mar 4, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122181 in the federal list. How to read these figures.