Purchases to support transit service for 6 communities near Petit-Rocher, New Brunswick.

Bathurst, New Brunswick

completePublic TransitRTSF
Federal contribution
$462,985
Federal share80%

of $578.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 17, 2025
20252026
Built

Approved 14 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Sep 1, 2025(actual)
Construction end
Mar 10, 2026(actual)

Against the original forecast

  • Construction start16 months lateforecast May 1, 2024
  • Construction end7 weeks earlyforecast May 1, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122182 in the federal list. How to read these figures.