Purchases to support transit service for Haut St-François and surrounding areas, Quebec.

Ascot Corner, Quebec

approvedPublic TransitRTSF
Federal contribution
$488,000
Federal share64%

of $765.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 24, 2026
20252026
BuiltForecast

Approved 18 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Jul 1, 2024(forecast)
Construction end
Oct 1, 2024(forecast)