Transit Feasibility Study for the Town of Amherst, NS

Cumberland County, Nova Scotia

underwayCapacity BuildingRTSF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 25, 2025
BuiltForecast

Approved 9 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Town of Amherst
Construction start
May 23, 2025(actual)
Construction end
Oct 30, 2025(forecast)

Against the original forecast

  • Construction start5 months lateforecast Jan 6, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 123043 in the federal list. How to read these figures.