Transit Feasibility Study for Fisher River Cree Nation, MB
Federal contribution
$45,000
Federal share90%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2026
2026
The source gives no usable construction span.
Approved 14 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Fisher River Cree Nation
- Construction start
- Apr 1, 2025(actual)
- Construction end
- Mar 14, 2025(forecast)
Against the original forecast
- Construction start3 months lateforecast Jan 2, 2025