Banook Canoe Club Revitalization

Halifax, Nova Scotia

underwayOtherGICB
Federal contribution
$2.3M
$2,339,736
Federal share80%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2025
202420252026
BuiltForecast

Approved 4 weeks before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Banook Canoe Club, Limited
Construction start
Sep 18, 2023(actual)
Construction end
Dec 1, 2025(forecast)

Against the original forecast

  • Construction start5 months earlyforecast Feb 12, 2024