Killarney and District Multipurpose Facility

Killarney, Manitoba

completeRecreationMRIF
Federal contribution
$500,000
Federal share8%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2007
2008
Built

Approved 4 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Killarney
Construction start
Feb 13, 2007(actual)
Construction end
Aug 1, 2008(actual)

Against the original forecast

  • Construction start17 months lateforecast Sep 1, 2005
  • Construction end5 months earlyforecast Dec 31, 2008

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12416 in the federal list. How to read these figures.