Wastewater System Improvements

Sussex Corner, New Brunswick

completeWastewaterMRIF
Federal contribution
$4,863
Federal share33%

of $14.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 23, 2008
20082009
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Sussex Corner
Construction start
Aug 31, 2007(actual)
Construction end
Aug 31, 2009(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Oct 17, 2007
  • Construction end12 months lateforecast Aug 31, 2008

Also in Sussex Corner

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12437 in the federal list. How to read these figures.