Swan Lake Lagoon

Swan Lake, Manitoba

completeWastewaterMRIF
Federal contribution
$584,644
Federal share22%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 24, 2006
200620072008200920102011
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Rural Municipality of Lorne
Construction start
Nov 1, 2008(actual)
Construction end
Mar 14, 2011(actual)

Against the original forecast

  • Construction start3.5 years lateforecast May 1, 2005
  • Construction end4.4 years lateforecast Oct 15, 2006