Arden Water Reservoir
Federal contribution
$220,000
Federal share28%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 9, 2007
200820092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Lansdowne
- Construction start
- Oct 9, 2007(actual)
- Construction end
- Feb 24, 2010(actual)
Against the original forecast
- Construction start2.3 years lateforecast Jul 1, 2005
- Construction end13 months earlyforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12622 in the federal list. How to read these figures.