Meadow Portage Community Council - Water Treatment Plant Upgrade

Meadow Portage, Manitoba

completeDrinking WaterMRIF
Federal contribution
$437,000
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2006
20072008200920102011
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Nov 23, 2006(actual)
Construction end
Mar 23, 2011(actual)

Against the original forecast

  • Construction start20 months lateforecast Apr 1, 2005
  • Construction end16 months lateforecast Dec 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12642 in the federal list. How to read these figures.