Back to projects

Matheson Island Lagoon

Matheson Island, Manitoba

completeWastewaterMRIF
Federal contribution
$177,000
Federal share33%

of $531.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2005
20062007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
May 17, 2005(actual)
Construction end
Apr 22, 2010(actual)

Against the original forecast

  • Construction end2.6 years lateforecast Oct 1, 2007