Pine Dock Solid Waste Disposal

Little Bullhead, Manitoba

completeSolid Waste ManagementMRIF
Federal contribution
$192,000
Federal share33%

of $576.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2005
20062007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Nov 1, 2005(actual)
Construction end
Apr 7, 2010(actual)

Against the original forecast

  • Construction start6 months lateforecast May 17, 2005
  • Construction end2.5 years lateforecast Oct 1, 2007