Pine Dock Solid Waste Disposal
Federal contribution
$192,000
Federal share33%
of $576.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2005
20062007200820092010
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community Council of Pine Dock
- Construction start
- Nov 1, 2005(actual)
- Construction end
- Apr 7, 2010(actual)
Against the original forecast
- Construction start6 months lateforecast May 17, 2005
- Construction end2.5 years lateforecast Oct 1, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12647 in the federal list. How to read these figures.