Bridge Replacement & Grid Reconstruction
Federal contribution
$3,856
Federal share25%
of $15.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 27, 2006
2006
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Big Arm
- Construction start
- Oct 31, 2005(actual)
- Construction end
- Aug 14, 2006(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 1, 2006
- Construction end8 months earlyforecast Mar 31, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12689 in the federal list. How to read these figures.