Beaubassin Research Centre Energy Upgrades

Aulac, New Brunswick

approvedOtherGICB
Federal contribution
$324,936
Federal share80%

of $406.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 29, 2026
2026
BuiltForecast

Approved 6 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Ducks Unlimited Canada
Construction start
Apr 15, 2025(forecast)
Construction end
Aug 15, 2026(forecast)