Tors Cove Hall Retrofit

Tors Cove Local Service, Newfoundland and Labrador

approvedOtherGICB
Federal contribution
$120,129
Federal share80%

of $150.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2026
2026
BuiltForecast

Approved 5 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Tors Cove Hall
Construction start
Feb 3, 2025(forecast)
Construction end
Aug 4, 2025(forecast)