Mission Road Grid Claycapping

Grayson, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$28,040
Federal share25%

of $112.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
2006
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 31, 2005(actual)
Construction end
Jan 26, 2006(actual)

Against the original forecast

  • Construction end2 months earlyforecast Mar 31, 2006

Also in Grayson