Lagoon Dredging Renewal
Federal contribution
$4,819
Federal share25%
of $19.3K total eligible cost; the rest comes from other partners.
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Denzil
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Sep 30, 2005(actual)
Against the original forecast
- Construction end6 months earlyforecast Mar 31, 2006
Also in Denzil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12800 in the federal list. How to read these figures.