Back to projects

Weigh Scale for the Landfill

Speers, Saskatchewan

completeSolid Waste ManagementMRIF
Federal contribution
$7,804
Federal share25%

of $31.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
2006
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 31, 2005(actual)
Construction end
Oct 12, 2006(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 8, 2005
  • Construction end11 months lateforecast Nov 1, 2005

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12827 in the federal list. How to read these figures.