Hamlet of Benson - BioFiltration System

Benson, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$18,021
Federal share25%

of $72.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
2006
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 31, 2005(actual)
Construction end
Jul 18, 2006(actual)

Against the original forecast

  • Construction end4 months lateforecast Mar 31, 2006

Also in Benson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12843 in the federal list. How to read these figures.