Village of Wilcox Lagoon Upgrade
Federal contribution
$44,940
Federal share25%
of $179.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
2006
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Wilcox
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Nov 19, 2006(actual)
Against the original forecast
- Construction end8 months lateforecast Mar 31, 2006
Also in Wilcox
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12885 in the federal list. How to read these figures.