Back to projects

Road Reconstruction

Gainsborough, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$65,474
Federal share25%

of $261.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2006
200620072008
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Oct 31, 2005(actual)
Construction end
Jan 9, 2008(actual)

Against the original forecast

  • Construction start5 months earlyforecast Apr 1, 2006
  • Construction end9 months lateforecast Mar 31, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12899 in the federal list. How to read these figures.