Water Treatment System Upgrade

Macoun, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$33,847
Federal share25%

of $135.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
20062007
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Macoun
Construction start
Jul 31, 2005(actual)
Construction end
Jan 8, 2007(actual)

Against the original forecast

  • Construction end9 months lateforecast Mar 31, 2006

Also in Macoun

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12904 in the federal list. How to read these figures.