Lagoon Expansion

Marshall, Saskatchewan

completeWastewaterMRIF
Federal contribution
$127,336
Federal share25%

of $509.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2006
2006200720082009
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Marshall
Construction start
Oct 31, 2005(actual)
Construction end
Dec 8, 2008(actual)

Against the original forecast

  • Construction start5 months earlyforecast Apr 1, 2006
  • Construction end4 months earlyforecast Mar 31, 2009

Also in Marshall

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12952 in the federal list. How to read these figures.