Ste. Rose du Lac Tourism Infrastructure Upgrade

Ste. Rose, Manitoba

completeTourismMRIF
Federal contribution
$87,310
Federal share33%

of $261.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2005
200620072008
Built

Approved 4 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Ste. Rose Du Lac
Construction start
May 17, 2005(actual)
Construction end
Mar 10, 2008(actual)

Against the original forecast

  • Construction end6 months earlyforecast Sep 1, 2008

Also in Ste. Rose

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12973 in the federal list. How to read these figures.