Grid Reconstruction
Federal contribution
$57,805
Federal share25%
of $231.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
2006
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Chester
- Construction start
- Aug 31, 2005(actual)
- Construction end
- Oct 15, 2006(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2005
- Construction end7 months lateforecast Mar 31, 2006
Also in Glenavon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13020 in the federal list. How to read these figures.