Grid Reconstruction

Glenavon, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$57,805
Federal share25%

of $231.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
2006
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Aug 31, 2005(actual)
Construction end
Oct 15, 2006(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2005
  • Construction end7 months lateforecast Mar 31, 2006