Belmont Lagoon Upgrades

Strathcona, Manitoba

completeWastewaterMRIF
Federal contribution
$460,000
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 24, 2006
2006200820102012
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 1, 2010(actual)
Construction end
Feb 28, 2012(actual)

Against the original forecast

  • Construction start4.6 years lateforecast Nov 17, 2005
  • Construction end11 months lateforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13098 in the federal list. How to read these figures.