Schedule
Announced and approvedDec 18, 2007
20082009201020112012
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Grey
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Mar 19, 2012(actual)
Against the original forecast
- Construction start4.3 years lateforecast Nov 30, 2005
- Construction end12 months lateforecast Mar 31, 2011