Back to projects

Brookdale Sewer System

Brookdale, Manitoba

completeWastewaterMRIF
Federal contribution
$160,000
Federal share20%

of $796.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 24, 2006
2006200720082009
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 1, 2008(actual)
Construction end
Oct 31, 2009(actual)

Against the original forecast

  • Construction start2 years lateforecast Jun 1, 2006
  • Construction end3.1 years lateforecast Oct 1, 2006