Wastewater Collection & Treatment
Federal contribution
$870,602
Federal share33%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.9 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Petitcodiac
- Construction start
- May 6, 2008(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 1, 2008
- Construction end2.6 years lateforecast Nov 30, 2008
Also in Petitcodiac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13155 in the federal list. How to read these figures.