Wastewater Collection & Treatment

Petitcodiac, New Brunswick

completeWastewaterMRIF
Federal contribution
$870,602
Federal share33%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.9 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Petitcodiac
Construction start
May 6, 2008(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2008
  • Construction end2.6 years lateforecast Nov 30, 2008